BACKGROUND
Signature Protocol of Agreement
Agreement signed with the State of Côte d'Ivoire to launch the project.
Signature of the Convention
Official signature of the concession agreement with the State.
Signature EPC Contract
Design and Construction contract signed with partner EPC.
Financial closure
Financing agreements signed with donors.
Work Start (NTP)
Official start-up order for construction work.
Gas Turbine coupling
First megawatts injected into the Ivorian network.
Coupling of the steam turbine
TECHNICAL & OPERATIONAL MONITORING
Beyond historical milestones, follow the technical evolution of the site and the day-to-day operation.
Steam turbine (TAV) in production
First Synchronization + TAV Coupling
Admission VAT Vapor
Vapour Hunting
First Vapor Production
End of Chemical cleaning of boiler
Tensioning of the main transformer of the TAV
Independent production of drinking water
Production of demineralized water
Hydraulic test of the recovery boiler
Performance testing
Îlotage test
Test to isolate the full load of the group. Piloting the TAG from the control room.
Technical tests
Power test, Full load rejection test, Specific fuel consumption test.
Change in Load
Load variation test.
First Flame
First Fire of the Gas Turbine.
Synchronization
First synchronization of the power plant to the network.
Switching
Turn the gas turbine.
TAG voltage setting
Powering the main transformer of the gas turbine.
Regulation Air
Commissioning of the control air compressor.
Connection 52G
Connection of the 52G gas turbine breaker.
Connection Post
Connection of the gas turbine main Transfo to the Taboth station.
Commissioning
Starting commissioning the Open Cycle.
TAV alternator
Place the turbine alternator in Vapor.
HP TAV body
Lays the High Pressure Body (HP) of the Vapour Turbin.
Body BP TAV
Lay down the low pressure body (BP) of the steam turbine.
Case & Alternator
Place the first case and arrive from the TAV alternator.
MP-LP body
Arrival of the MP-LP body of the steam turbine.
Transfo TAV Transfer
Transfer of the main TAV transfo from the port to the ATINKOU power plant.
Transfer Transfo TAG
Transfer of the main TAG transfo from the port to the ATINKOU power plant.
HRSG modules
Unload modules from the Recovery Boiler (HRSG) at port.
HP Corps arrival at the plant
Arrival of the HP body from the steam turbine at the ATINKOU thermal power plant.
HP Corps arrival at port
Arrival of the HP body from the steam turbine in port.
Command Modules
Installs electrical control modules.
TAG lineage
Fitting gas turbine, alternator and lineage.
Circuit breaker 52G
Installation of the TAG 52G Group Circuit Breaker.
TAG Assembly
Mounting of the Gas turbine and its Alternator.
TAG transfer
Transfer of the Gas Turbine and Alternator from Abidjan port to the power station.
TAG Massif
Bounding of the turbine/alternator massif. Gas turbine ready for transport.
First Massifs
Concreteing of the first massifs.
Foundations
Achievement of the pious.
Earthworks
Earthworks in progress.
Order of Service
Order of Service issued to the EPC.
AOT Signature
Signing of the Temporary Occupancy Order (AOT).
Land
Provision of the site and start of clearing.
Financing
Signature of funding documents and Amendment to the Convention.
EPC contract
Signing of the EPC contract with TSK and Addendum Engineer Consulting (TRACTEBEL).
Convention
Signature of the Convention between ATINKOU and the State of Côte d'Ivoire.
Protocol of Agreement
Signing of the Protocol of Agreement with the State of Côte d'Ivoire.

